(See Page 1 ).

SUMMARY OF CIDDA
COST RESEARCH from
an independent analysis
by EC Harris

 

cast iron pipes to BS EN 877, while considerably cheaper to supply and install than the old pipes with caulked joints, will in most situations be more expensive than PVC based systems.

COMPETITIVENESS IMPROVED

Nevertheless, the price disadvantage of the new cast iron products was less significant than expected. The study indicates that the old cast iron system was very expensive and it is to a very great extent this perception of high cost that still remains today among both contractors and consultants.

Labour constants for the BS EN 877 new pipes are dramatically reduced compared to the old systems. To an extent the EC Harris research found that the CIDDA assumptions on labour constants were correct. The established times used in the price books for making a joint in a straight run of underground drainage showed a lack of consistency between price books. One price book suggested that a metre run of 100mm diameter mechanically jointed pipe, laid in a trench bottom should take 0.55 labour hours of advanced plumber and 0.55 hours of apprentice plumber. This equates to 1.1 hours of total labour time per metre run or 3.3 hours for a 3m length of pipe. To put it another way one man would be expected to lay only 3 pipes in a working day and even then he would need to work 2 hours overtime to achieve this.

To validate the new built-up rates, contractor's estimators were approached. The perceived opinion was that the build up of rates was reasonable. One contractor came back and said that their labour constants were lower than the ones calculated in the research.

NOW REFLECTED IN PRICE BOOKS

On completion of the research, the producers of the main building prices guide books were contacted to update their records. Davis Langdon and Everest, producers of SPONS accepted the research and applied the new rates to their price guides, Griffiths price guide also following suit. The latest SPONS guide (2001), now lists labour time and costs of the BS EN 877 cast iron systems lower than uPVC solvent weld systems which emphasises, speed of installation of the mechanical joints.

BENEFITS

There are a number of benefits a cast iron pipe system implies. Cast iron is less likely to suffer physical damage in exposed situations and is less susceptible to damage during the course of construction work.

As mentioned previously, there are also associated benefits in terms of fire resistance and sound insulation properties which need to be taken into account when determining the competitiveness of cast iron against alternatives.

Cast iron also requires minimal maintenance and in normal use will last the full 60 years normally taken as a building's life. For clients with a long term view, cost-in-use calculations could well indicate that a cast iron system will provide an economic solution. This benefit is now being utilised in the growth of PFI projects.

COST BENEFIT ANALYSIS/RISK ASSESSMENT

When conducting a cost benefit analysis it is important to consider the issue of business risk associated with a failure of the drainage system. Clearly this takes on significant proportions in the case of revenue sensitive operations such as supermarkets, and high priority use buildings such as hospitals.

SPECIFIER TO DETERMINE 'VALUE' VERSUS 'COST'

Having recognised that the use of cast iron is likely to be more expensive than alternative materials, the key question for building owners and specifiers is of course, 'under what circumstances will it be worth paying the extra?' This involves a consideration of costs versus benefits and risk analysis.


Click on the graph for a larger view
Below Ground - Total Drainage Cost
When one expresses the cost against the total cost of the drainage installation ie. including trenches, backfill, earthwork support and the like, the cost of new cast iron adds 25% compared with clay, and 47% compared with uPVCs. The old mechanically jointed and caulked systems would add 13% and 59% respectively to the cost of using the new pipes and fittings.

CI 1 - Below ground, mechanically jointed BS437
CI 2 - Below ground, caulked jointed BS437

Above Ground - Total Drainage Cost
If one again takes into account the total drainage installation cost, then new cast iron is 62% more expensive than PVC-u and the reductions against mechanically jointed and caulked systems become 34% and 49% respectively.

CI 1 - Above ground, mechanically jointed BS416
CI 2 - Above ground, caulked jointed BS416

 


If you would like further information, please fill in the
appropriate details on the Further Information page,
call the
CIDDA telephone hotline +44 (0)121 693 9909
or E-mail info@cidda.com